On Monday, pews were moved to one side of the Nave in preparation for new tile installation and the platform around the altar was removed. The platform will be rebuilt... read more →
The polished concrete floor process has started in the Narthex, hallway, and vesting sacristies. .... and by the end of the week, they were completed for everyone to enjoy on... read more →
Old building, old pipes. While it is not ideal to have to take on unexpected plumbing repairs, I am thankful they showed up during renovations so that it can all... read more →
It was a really dusty week as renovation work focused on the Parish Hall floors. There have been several passes of grinding, each at incrementally finer grit on the machines.... read more →
The four middle stained glass panels at the back of the Nave were removed yesterday. They will be relocated to the Parish Hall where they will be set up to... read more →
The heavy equipment has been brought in. These machines will be used to grind, vacuum, and polish our concrete floors to a clean, modern look in the Parish Hall and... read more →
The new LED lights for the the Parish Hall classrooms and hallways arrived yesterday. The lights are starting to be installed and (even though the pictures don't do it justice)... read more →
This week has been about the three P's: plumbing, painting, and panels. Part of the concrete slab was cut out in the kitchen to replace part of a drain pipe... read more →
All the hallways and classrooms that have drop ceilings are getting new modern ceiling tiles. These tiles are more uniform in their appearance (no little holes) than the old ones.... read more →
Painting continues in the Parish Hall as the beams get a fresh coat going from brown to Urbane Bronze. This color coordinates well with the main color for the walls: Anew Gray.... read more →